Once the S700 line has been placed in the area chosen for installation, you can proceed to assembly the mechanical and electrical connection between them.

In particular, the S700-GL, S700-SP and S700-WP machines are connected to each other through the aspirated conveyor belt, which therefore determines the reciprocal position through the fastening systems placed on each of them.

The first task to do is to assemble the conveyor belt on the S700-SP, by adjusting the height of the supports using a level, until the conveyor belt reaches the right planarity. Proceed with the positioning of the S700-GL and its leveling, followed by the S700-WP, at the other end of the conveyor belt, which is also leveled and then secured to the conveyor belt itself.

After the positioning of the three machines described above, place the S700-QS in its position, making sure that it doesn't damage the supports of its output mat against the S700-SP.

Once the positioning is completed, insert the rails below it and fix themto the ground, leveling the machine with the dedicated pushers.

Now that all the S700 line is placed, wire the machines together and connect them to the external power supply.